Get in touch

Submit

Thank you for getting in touch. We will be in contact shortly.

Project Overview

Keegans is proud to deliver another successful fire remediation project for Abri Group in collaboration with Design Build Facades. We utilised our expertise in Fire Engineering, Project Management, Quantity Surveying, Clerk of Works and Principal Designer to deliver a high-quality, safe building for residents.

 

Background

Park Reach is a relatively newly built development, consisting of 59 residential apartments, located in Southampton. The eastern wing of the building has 8 duplex apartments over 3 storeys (ground to 2nd floor) and the western wing has 51 apartments over 6 storeys (ground to 5th floor). Whilst the building is over 11m it does not fall into the definition of a Higher Risk Building (HRB) as it comprises of 6 storeys.

 

Abri had previously commissioned surveys which identified that the building had been partially clad with combustible insulation material. This contractor was appointed to propose a design solution under a Design and Build contract.

 

Scope of Work

The works included the replacement of combustible external wall cladding and insulation, to both the cladding and brickwork sections, and replacing them with non-combustible materials, including the replacement of defective cavity barriers. The client’s objective was to obtain an A1 EWS1 rating and the proposals included the application of a metal cladding system and a Rainscreen panel system.

 

Keegans' Role

Keegans were appointed to manage the cladding replacement project and ensure that works were carried out in accordance with the specification and current Fire Regulations.

 

Employers Agent and Project Management

We provided Project Management including issuing certificates of Practical Completion and Completion of Defects Liability, chairing monthly site progress meetings, and issuing minutes to the site directory. This included the drafting of Employers Requirements and the development and agreement of a Contract Sum Analysis (CSA) on which the contract documents and contract sum were agreed.

 

We undertook the projects commercial role including reviewing the contractors detailed RIBA Stage 4 proposals and costs, interim progress valuations and certification of the same, and final account agreement, again certifying of the same.

 

Fire Engineering

Our Fire Engineer reviewed the detailed design drawings, and provided a technical design review of the proposed plans/scope of works to ensure they were compliant to the Building Regulations functional requirements. This included commenting on the ongoing maintenance implications of providing an EWS1 form to Option B1 at the end of the works.

 

Clerk of works

Our Clerk of Works attended site and carried out regular quality inspections and sign off completed works.

 

Construction Design and Management

Our Principal Designer advised the client on the details of the existing information relating to the building and assembly and issue of preconstruction information. We issued a F10 on behalf of the Client. We completed a review the contractors CDM proposals and provided an ongoing CDM role in relation to development of the design and assembled and issued the H&S upon completion

 

Challenges and Solutions

One of the key project challenges was the remedial works to brickwork sections (the removal of combustible insulation and installation of cavity barriers). The original proposal was designed so that works were undertaken internally within flats, requiring the removal of internal wall finish and reinstatement. However, there was concern raised by the client team about the associated disruption to residents and potential delays caused by access issues. We reviewed this with the contractor to find an alternative, less intrusive and cost/programme-neutral option. An external working option was agreed upon following an external trial and technical review. This methodology was favourably received by the residents and provided an overall cost saving and was programme-neutral.

 

Resident Communication and Engagement

Abri and Design Build Facades notified the residents of the works in advance of commencement. There was regular communication with the residents throughout the project, including programming, sequencing of works and health & safety matters.  Keegans attended resident consultation events to support Abri. Ensuring lines of clear and timely communication between the residents, client and contractor was important in the success of this project.

 

Project Completion

The completed project was handed over to the client on time and to budget in April 2024, delivering a high-quality, safe building for the residents.

 

Continue reading about Park Reach | Cladding Remediation by KeegansRead less

Get in touch

Submit

Thank you for getting in touch. We will be in contact shortly.